The Hydrologic Analysis Report was approved by ConnDOT on May 13, 2010.
Bailiwick Bridge Final Hydrologic Report – Approved May 2010 (click on title to review report)
Revised Draft Hydrologic Analysis Report submitted to Town 12/18/09.
The Town of Greenwich approved the expanded scope of services for the hydrologic analysis. To review the expanded scope click on the italics text – Hydrologic Analysis Expanded Scope of Work
Hydrologic Analysis scope expanded and submitted to Town of Greenwich.
A hydrologic report was completed and submitted to the Town of Greenwich on October 15, 2009.
A wetlands study report has been completed by William Kenny Associates, LLC for Dewberry. Wetlands Study Report – Bailiwick Road Bridge To review the report click on the italics text.
Wetland and watercourse delineation completed July 31, 2009.
As part of the preliminary design, Dewberry will commence with the field topographical survey the week of August 3, 2009.