Bailiwick Road Bridge over the Byram River
Rehabilitation of Bridge #05491
Town of Greenwich, Connecticut
  • Home
  • Project Status
  • Scope
  • Project Photos
  • Notices
  • FAQ
  • Hydrologic Analysis Report Approved
    Project Status

    The Hydrologic Analysis Report was approved by ConnDOT on May 13, 2010.
    Bailiwick Bridge Final Hydrologic Report – Approved May 2010 (click on title to review report)

    Revised draft Hydrologic Analysis Report submitted
    Project Status

    Revised Draft Hydrologic Analysis Report submitted to Town 12/18/09.

    Hydrologic Analysis Expanded Scope Approved
    Project Status

    The Town of Greenwich approved the expanded scope of services for the hydrologic analysis.   To review the expanded scope click on the italics text – Hydrologic Analysis Expanded Scope of Work

    Hydrologic Analysis Scope Expanded
    Project Status

    Hydrologic Analysis scope expanded and submitted to Town of Greenwich.

    Public Information Meeting Minutes 09-22-09
    Notices, Project Status
    Hydrologic Report Completed
    Project Status

    A hydrologic report was completed and submitted to the Town of Greenwich on October 15, 2009.

    Wetlands Study Report Completed
    Project Status

    A wetlands study report has been completed by William Kenny Associates, LLC for Dewberry.  Wetlands Study Report – Bailiwick Road Bridge  To review the report click on the italics text.

    Field Survey Completed
    Project Status

    Field survey completed August 15, 2009.

    Wetland and Watercourse Delineation
    Project Status

    Wetland and watercourse delineation completed July 31, 2009.

    Field Topographical Survey to Commence
    Project Status

    As part of the preliminary design, Dewberry will commence with the field topographical survey the week of August 3, 2009.